Downers' project update on the Chatham Islands Airport runway extension for the period 25 February to 10 March states ,
Since our last update we have:
- Completed the final paving of the existing runway
- Completed asphalt paving in the airport carpark
- Completed carting aggregates on North Rd
- Commenced removal of old taxiway
- Install Sewer system for terminal building
- Voyage 6 – went according to plan
Key construction activity we will be doing in upcoming works
- - Concrete in approach lights
- - Topsoil and grassing
- - Disestablishment of Asphalt plant
- - Voyage 7 – Disestablishment of plant on 25 March 2023