Almost Done

 

Downers' project update on the Chatham Islands Airport runway extension for the period 25 February to 10 March states , 

Since our last update we have:

  • Completed the final paving of the existing runway
  • Completed asphalt paving in the airport carpark
  • Completed carting aggregates on North Rd
  • Commenced removal of old taxiway
  • Install Sewer system for terminal building
  • Voyage 6 – went according to plan

Key construction activity we will be doing in upcoming works 

  • - Concrete in approach lights
  • - Topsoil and grassing
  • - Disestablishment of Asphalt plant
  • - Voyage 7 – Disestablishment of plant on 25 March 2023